Purpose and Scope of Project:
To repair the existing metal roof and replace the low-sloped pvc roofing system.
Amount of Contract:
$35,364.00
Funding Source
Project # Public Works Complex - Equipment Maintenance Building-Roof RepairsDiscretionary Funds 
Project String 20002000-48010Contract Number:2872
Budget Amendment        REDUCE     INCREASE 
Grant Funds Matching Funds 